Earthworks Drainage & Consolidation

Drainage Layer, Pozidrain G - Magna Park, Lutterworth, UK

Client Gazeley (GLP) Ltd
Contractor

Mick George Contracting Ltd

Consultant Hydrock Consultants Ltd
Product

Pozidrain G Geocomposite

Quantity

400,000 m²

Benefits

– High flow capacity in both directions
– Accelerated consolidation
– Large rolls for fast installation
– Saving 80,000 m³ of drainage stone
– Substantial 86% CO2 saving

Project Description

Magna Park in Lutterworth provides a high-quality business park environment specifically focused on logistics and distribution. Covering over 550 acres, it is bounded by the M1, M6 and M69 motorways, making it the first choice for logistics due to its strategic position in the centre of the country.

Home to 29 different occupiers, with 8.3 million sq ft (771,155 sq m) of sustainable logistics floor space and 32 buildings, Magna Park is Gazeley’s flagship distribution park. Since the development of the Park in early 1988, Magna Park’s continuous growth has contributed significantly to the development of the local economy and infrastructure.

Gazeley appointed Hydrock Consultants to design the enabling works for Magna Park South and commissioned Mick George to complete the earthworks operations required on this groundbreaking development, widely regarded as Europe’s premier logistics location.

The Challenge

A substantial amount of earthworks and ground improvement were required to facilitate construction of the distribution centres and the main programme objectives were to accelerate consolidation, reduce construction time and deliver carbon savings by eliminating the use of drainage stone. An innovative and cost effective design solution was needed to enable fast consolidation since a large proportion of the development was constructed on weak ground, where it was necessary to first drain the sub-formation using prefabricated vertical drains (PVDs). The geosynthetic design required a high performance geocomposite drainage layer to discharge the water from the PVDs.

The Solution

The designer Hydrock, working with ABG, developed a geosynthetic solution that would provide efficient drainage to ensure consolidation of the sub-formation and the embankment fill.

The Pozidrain G geocomposite drainage layer was used to provide drainage above the 150mm Class 6C platform and PVDs at a 1.5m grid spacing. Pozidrain was also installed within the embankment fill at 3m vertical spacings to provide accelerated consolidation.

The use of Pozidran G geocomposite instead of drainage stone resulted in an impressive 86% / 2,998 tons of CO2 saving in this design.

ABG Pozidrain G Geocomposite specifically designed for consolidation applications

The ABG Service

ABG provided technical advice and design assistance and on this large project it was important to carefully coordinate deliveries to ensure efficient installation and meet the required completion deadline.

Contact ABG today to discuss your consolidation project requirements and discover how ABG past experience and innovative products can help.

Additional information