Tunnel Invert Drainage

Cavidrain Invert, Brynglas Tunnel, M4 Motorway, Newport, UK

Project Information

Client:Welsh Government
Contractor:Costain Ltd
Consultant:Capita Symonds Consultancy
Product:Cavidrain Invert 20
Quantity8,000m2
Benefits:- Improved drainage capacity
- Materials and labour cost reduction
- Reduced installation requirements compared to traditional invert drainage methods
- Rapid installation

Project Description

The Brynglas Tunnel is situated on the M4 Motorway under Brynglas Hill in Newport, South Wales. The 370m twin-bored tunnels were the first tunnels in the British motorway network and are still the only bored tunnels. The tunnels and adjacent M4 motorway Usk Bridge were originally planned by Newport Corporation in 1959. Work started on the £3m tunnels in 1962. Both structures were complete and open to traffic on 5th May 1967. Almost as soon as the M4 Newport bypass (junctions 24-28) had opened, the traffic levels had grown to such a degree that the road had to be widened to three lanes in each direction. This was finished in 1982 but with the exception of the tunnels and Usk Bridge which remained as dual two-lane sections (Junctions 25-26). The Authority approached Capita Symonds Consultancy to design and supervise the reconstruction of this important tunnel on the M4 motorway.


The Challenge

The requirement was to refurbish the tunnel and design a drainage solution that would enable fast installation on this very busy motorway. 

The traditional method using drainage stone was considered outdated, costly and inadequate. A cost saving technique and innovative design was required for the reconstruction of this critical tunnel on the M4 motorway.

A key aim of the design strategy was to minimise the required installation time and enable each section to be completed within the six-hour night time closure window.

The Solution

Capita Symonds acting as the designer worked with ABG to develop a geosynthetic solution that would provide adequate drainage, fast installation and reliable long term performance. Cavidrain Invert 20 drainage layer was specified and installed with 80mm of fast setting screed (10N/mm2 in 3hr), 250mm reinforced concrete slab and 135mm asphalt overlay on top. The concrete filled the Cavidrain geocomposites cuspates to create interconnecting drainage channels, ensuring high flow capacity.

Cavidrain Invert drainage geocomposites showing water flow areas for tunnel drainage

The ABG Service

ABG provided technical advice and design assistance on this tunnelling project. This included a trial installation, site meetings and coordinating time sensitive deliveries with the contractor.

ABG provided technical advice and design assistance on this tunnelling project. This included a trial installation, site meetings and coordinating time sensitive deliveries with the contractor.ABG provided technical advice and design assistance on this tunnelling project. This included a trial installation, site meetings and coordinating time sensitive deliveries with the contractor.
Concrete core sample showing drainage channelsConcrete core sample showing drainage channels
Tunnel Invert Drainage GeocompositeTunnel Invert Drainage

Contact ABG today to discuss your tunnel project and drainage specific requirements and discover how ABG past experience and innovative products can help on your project.

Cavidrain Invert

Cavidrain® Invert provides a pre-formed drainage layer into which the concrete floor slab can be easily cast. Cavidrain® Invert replaces the crushed stone and pipes traditionally used to collect and transport away infiltration water.

more...

Cavidrain Invert geocomposite for tunnel invert drainage
 

Products

Cavidrain Invert

Cavidrain® Invert provides a pre-formed drainage layer into which the concrete floor slab can be easily cast. Cavidrain® Invert replaces the crushed stone and pipes traditionally used to collect and transport away infiltration water.

more...

Cavidrain Invert geocomposite for tunnel invert drainage
 

Downloads

 

Login for Access